Project Update Peregrine Estate, Piara Waters February 2017

Stage 1 Civil works have been completed Clearances have been requested from the authorities Deposited Plan has been lodged with landgate Once all clearances have been received they will be lodged and titles will issue Titles are expected in mid-March Stage 2 Civils works are underway with most items complete Sewer and water lines are […]

» Read more

Project Update The Springs, Midland February 2017

Public artwork is currently being fabricated. First floor brickwork is complete. Floor scrape and clean is complete. Roof and wall trusses have been loaded. Roof and wall trusses are installed to 4 of the 6 buildings. Cabinets have been measured and are being manufactured. Balustrades have been measured and are being manufactured. Over the next […]

» Read more

Project Update Red Castle, Laithlain February 2017

The agreed schedule has been affected slightly by the weather with 5 days of EOT’s requested and approved. In light of this BGC is on schedule with all critical path items under control. Tower remedial works are now complete. Lighting of the turret is complete. Main Roads Department have left site after the completion of […]

» Read more

Project Update Bottleyard 75-99 Palmerston Street, Perth February 2017

Wet weather has caused a few delays to the communal area progress. The rain is preventing us from screeding and tiling the ground floor common areas. Scaffolding is coming down, with only a small amount to come down internally, on A block and C block. Works have commenced in the south atrium with planter boxes […]

» Read more

Project Update Peregrine Estate, Piara Waters December 2016

The forward earthworks has been completes to all stages with over 245,000m³ of sand now on site Stage 1 Civil works are nearing completion with the installation of manholes to connect Peregrine Estate to the existing infrastructure. Furniture (taps, power domes, sewer risers) are being set Retaining walls are complete Kerbs have been installed Manholes […]

» Read more

Project Update The Springs, Midland December 2016

Suspended slab poured and cured for 80% of the build. Edge-forms have been stripped or about to be stripped. Scaffolding installed to first floor. Hoist to first floor has been installed. Brickwork to parts of first floor build has been loaded. Brickwork commenced on first floor for 2 (out of 6) of the buildings. CLICK […]

» Read more

Project Update Red Castle, Laithlain December 2016

The builder BGC is ahead of schedule with all critical path items under control. Tower works are almost complete. Painting is complete, roof is complete, brickwork is complete, and windows have been installed. Lighting to the tower will commence this week. Scaffolding will be removed in the next 2 weeks. Engineer sign off has been […]

» Read more

Project Update Bottleyard 75-99 Palmerston Street, Perth December 2016

Tower crane has been removed from site, lid has been poured to the lift shaft and the lift is being installed We are still ahead of schedule and on track to be complete at the end of March/Early April with titles in late April or Early May All ground floor apartments are complete with the […]

» Read more